Fanatics 3 - Frazeyburg, Ohio
This location for Fanatics required (3) P60 glass turnstiles installed side-by-side, replacing the existing doors. We had to demo a large wall to make them fit, install the new turnstiles and wire the EntraPass Global Edition Access Control System.
The Ohio installation was part of an 18-day trip – Start to Finish — Flew to Ohio, Drove to Florida, flew back to Colorado.
Completed Photos
Day 5 - Entrance 2
Another area of the same facility needed access control.We set up and placed the turnstiles on the open manufacturing floor, wiring them with EntraPass KT – 400 Controllers. Then, fence was installed to separate the secured and unsecured side.
Day 4
Wiring the EntraPass KT– 400 Controllers
Day 3
Fabrication of the P60s
Day 2
After removing the doors and false walls, we put in a new header channel, taped, mudded
and prepared our EntraPass Access Control Cable for the Turnstiles.
Installation Photos: Day 1
This project required (3) P60 glass turnstiles installed side-by-side, replacing the existing glass doors.
We had to demo this wall to make them fit.
Completed Work
Thank You to everyone in Ohio and at all of the Fanatics locations!